Clallam PUD / 2015–2026

Enterprise infrastructure & resilience

My infrastructure work spans the utility’s server platforms, storage, recovery and lifecycle upgrades. Recent automation makes the maintenance sequence explicit: establish readiness, perform the approved change, then verify the services people depend on.

My role

Platform administration, upgrade planning, automation design and implementation

Server maintenance / 2026 pilot

01Establish readiness

Select the server and check dependencies

02Control the change

Run the approved maintenance

03Verify service

Check operation after the reboot

A staged maintenance framework, tested in an initial pilot.

2015–2023

Maintain the core platforms

Maintained and upgraded virtual infrastructure, physical server clusters and storage. The work included VMware version upgrades, backup and recovery improvements, a NetApp-backed recovery instance and infrastructure support during the move into new facilities.

Responsibility over time

Server reliability and recovery remained part of my role alongside GIS, SCADA and NISC implementation work.

2026

Check protection at the VM level

Developed AWS Backup reporting that reconciles unique virtual machines against expected coverage and prior results. It identifies missing jobs, duplicate runs, failures followed by recovery, and completed jobs reporting zero protected bytes.

Operating evidence

A July 2026 report accounted for 69 expected VMs. The checks make omissions visible alongside job status; backup completion alone does not establish a successful restore.

2026

Make maintenance verifiable

Designed a PowerShell-first maintenance framework using managed service accounts and constrained JEA endpoints. Selected this approach over an Azure Arc / Update Manager-first design because per-server cost and subscription access complicated that path. Separate readiness, approved change and service-verification stages retain structured results.

Pilot result

The first patch-and-reboot pilot caught a printing regression, which was repaired. A later pilot stopped for an offline plotter. These are pilot results; estate-wide rollout remains staged.

2026

Modernize the Windows baseline

Provisioned Windows Server 2025 on VMware with EFI Secure Boot, Credential Guard, domain integration and monitoring.

Validation

Configuration checks and notification delivery were verified. Remaining operational acceptance items are tracked separately.

Technical environment

VMware vCenter / ESXi · Windows Server · NetApp · AWS Backup · PowerShell / PowerCLI · Python · gMSA · JEA